M3/4/5 - RhinoEdge development

Solution

Activity

Deliverable

Timing

Horn+implant

Schematic concept based on WisentEdge

Schematic design release

October

Horn

Old rhino tracker performance review

List of design changes

October

Horn+implant

GPS antenna selection and optimization

Selected and tested antenna

October

Horn

LoRaWAN antenna selection

Selected and tested antenna

October

Horn

Battery selection

Selected and tested battery

November

Horn

Hardware design of 1st prototype horn

Hardware design release

November

Horn

1st prototype horn bring-up and testing

Demonstration - 5pcs to be sent to PeaceParks

November

Horn+implant

Firmware development of basic functionality

Demonstration

November

Horn

2nd prototype revision and testing

Schematic and hardware design release

November

Implant

Implant mechanical prototyping

Hardware design

November

Horn

Field testing of horn tracker

Demonstration

December

Implant

Schematic and hardware design of 1st implant prototype

Schematic and hardware design release + send 2pcs to be sent to PeaceParks

December

Implant

Antenna design and selection for implant

Selected and tested antenna

December

Implant

1st prototype implant bring-up and testing

Demonstration

December

Implant

Field-testing non-implanted

Test results

December

Horn+implant

Communication from implant to horn testing

Demonstration

December

Implant

2nd prototype revision

Schematic, hardware, firmware design release

January

Implant

Field-testing implanted domestic animal

Test results

January

Horn

Hardware revision of horn for production

Schematic, hardware, firmware design release

January

Implant

Hardware revision of implant for production

Schematic, hardware, firmware design release

January

Last updated