M3/4/5 - RhinoEdge development
Solution | Activity | Deliverable | Timing |
Horn+implant | Schematic concept based on WisentEdge | Schematic design release | October |
Horn | Old rhino tracker performance review | List of design changes | October |
Horn+implant | GPS antenna selection and optimization | Selected and tested antenna | October |
Horn | LoRaWAN antenna selection | Selected and tested antenna | October |
Horn | Battery selection | Selected and tested battery | November |
Horn | Hardware design of 1st prototype horn | Hardware design release | November |
Horn | 1st prototype horn bring-up and testing | Demonstration - 5pcs to be sent to PeaceParks | November |
Horn+implant | Firmware development of basic functionality | Demonstration | November |
Horn | 2nd prototype revision and testing | Schematic and hardware design release | November |
Implant | Implant mechanical prototyping | Hardware design | November |
Horn | Field testing of horn tracker | Demonstration | December |
Implant | Schematic and hardware design of 1st implant prototype | Schematic and hardware design release + send 2pcs to be sent to PeaceParks | December |
Implant | Antenna design and selection for implant | Selected and tested antenna | December |
Implant | 1st prototype implant bring-up and testing | Demonstration | December |
Implant | Field-testing non-implanted | Test results | December |
Horn+implant | Communication from implant to horn testing | Demonstration | December |
Implant | 2nd prototype revision | Schematic, hardware, firmware design release | January |
Implant | Field-testing implanted domestic animal | Test results | January |
Horn | Hardware revision of horn for production | Schematic, hardware, firmware design release | January |
Implant | Hardware revision of implant for production | Schematic, hardware, firmware design release | January |