Solution
Activity
Deliverable
Timing
Horn+implant
Schematic concept based on WisentEdge
Schematic design release
October
Horn
Old rhino tracker performance review
List of design changes
October
Horn+implant
GPS antenna selection and optimization
Selected and tested antenna
October
Horn
LoRaWAN antenna selection
Selected and tested antenna
October
Horn
Battery selection
Selected and tested battery
November
Horn
Hardware design of 1st prototype horn
Hardware design release
November
Horn
1st prototype horn bring-up and testing
Demonstration - 5pcs to be sent to PeaceParks
November
Horn+implant
Firmware development of basic functionality
Demonstration
November
Horn
2nd prototype revision and testing
Schematic and hardware design release
November
Implant
Implant mechanical prototyping
Hardware design
November
Horn
Field testing of horn tracker
Demonstration
December
Implant
Schematic and hardware design of 1st implant prototype
Schematic and hardware design release + send 2pcs to be sent to PeaceParks
December
Implant
Antenna design and selection for implant
Selected and tested antenna
December
Implant
1st prototype implant bring-up and testing
Demonstration
December
Implant
Field-testing non-implanted
Test results
December
Horn+implant
Communication from implant to horn testing
Demonstration
December
Implant
2nd prototype revision
Schematic, hardware, firmware design release
January
Implant
Field-testing implanted domestic animal
Test results
January
Horn
Hardware revision of horn for production
Schematic, hardware, firmware design release
January
Implant
Hardware revision of implant for production
Schematic, hardware, firmware design release
January